ACA Logo

Threshold Test Ban Treaty (TTBT)

Treaty Between the United States of America and the Union of Soviet Socialist Republics on the Limitation of Underground Nuclear Weapon Tests (and Protocol Thereto)

Narrative
Text
Protocol

 

The Treaty on the Limitation of Underground Nuclear Weapon Tests, also known as the Threshold Test Ban Treaty (TTBT), was signed in July 1974. It establishes a nuclear "threshold," by prohibiting tests having a yield exceeding 150 kilotons (equivalent to 150,000 tons of TNT).

The threshold is militarily important since it removes the possibility of testing new or existing nuclear weapons going beyond the fractional-megaton range. In the 1960s, many tests above 150 kilotons were conducted by both countries. The mutual restraint imposed by the Treaty reduced the explosive force of new nuclear warheads and bombs which could otherwise be tested for weapons systems. Of particular significance was the relationship between explosive power of reliable, tested warheads and first-strike capability.

The task of negotiating a comprehensive test ban remained on the agenda of the U.S. Government, and, in Article I, the parties to the Threshold Test Ban Treaty undertook an obligation to continue negotiations toward that goal.

The first proposal for stopping nuclear weapon tests was made in 1955, and the first major negotiations with the Soviet Union for an effectively controlled test ban began in Geneva in 1958, with the United Kingdom also participating. The Conference on the Discontinuance of Nuclear Weapon Tests produced no agreement. The problem of working out verification procedures to ensure compliance with a complete ban on nuclear weapon tests in all environments proved to be intractable at that time. The procedures deemed necessary by the United States and the United Kingdom were not acceptable to the Soviet Union.

In 1963 the Limited Test Ban Treaty (LTBT) was signed by the Soviet Union, the United States, and the United Kingdom. This Treaty prohibits nuclear weapon testing in the atmosphere, in outer space and under water. The parties also agreed not to carry out any nuclear weapon test, or any other nuclear explosion, in any other environment -- i.e., underground -- that would cause radioactive debris to be present beyond the borders of the country in which the explosion took place.

Underground nuclear explosions were not prohibited by the 1963 Treaty, although both in the Treaty preamble and Article I, the LTBT parties pledged to seek "the discontinuance of all test explosions of nuclear weapons for all time...."

The United States and Soviet Union agreed in the spring of 1974 to pursue the possibilities of further restrictions on nuclear testing. Accordingly, a team of U.S. experts was sent to Moscow for technical talks.

Agreement on the Threshold Test Ban Treaty was reached during the summit meeting in Moscow in July 1974. The Treaty included a protocol which detailed technical data to be exchanged and which limited weapon testing to specific designated test sites to assist verification. The data to be exchanged included information on the geographical boundaries and geology of the testing areas. Geological data -- including such factors as density of rock formation, water saturation, and depth of the water table -- are useful in verifying test yields because the seismic signal produced by a given underground nuclear explosion varies with these factors at the test location. After an actual test has taken place, the geographic coordinates of the test location are to be furnished to the other party, to help in placing the test in the proper geological setting and thus in assessing the yield.

The Treaty also stipulates that data will be exchanged on a certain number of tests for calibration purposes. By establishing the correlation between stated yields of explosions at the specified sites and the seismic signals produced, this exchange improved assessments by both parties of the yields of explosions based primarily on the measurements derived from their seismic instruments. The tests used for calibration purposes may be tests conducted in the past or new tests.

Agreement to exchange the detailed data described above represented a significant degree of direct cooperation by the two major nuclear powers in the effort to control nuclear weapons. For the first time, each party agreed to make available to the other data relating to its nuclear weapons test program.

The technical problems associated with a yield threshold were recognized by the sides in the spring of 1974. In this context the Soviet Union mentioned the idea of some kind of a "mistakes" understanding concerning occasional, minor, unintended breaches. Discussions on the subject of such an understanding took place in the autumn of 1974 and in the spring of 1976. The Soviet Union was informed by the United States that the understanding reached would be included as part of the public record associated with submitting the Treaty to the Senate for advice and consent to ratification. The entire understanding is as follows:

Both Parties will make every effort to comply fully with all the provisions of the TTB Treaty. However, there are technical uncertainties associated with predicting the precise yields of nuclear weapons tests. These uncertainties may result in slight, unintended breaches of the 150 kiloton threshold. Therefore, the two sides have discussed this problem and agreed that: (1) one or two slight, unintended breaches per year would not be considered a violation of the Treaty; (2) such breaches would be a cause for concern, however, and, at the request of either Party, would be the subject for consultations.

The Soviet Union was also informed that while the United States would not consider such a slight, unintentional breach a violation, the United States would carefully review each such breach to ensure that it is not part of a general attempt to exceed the confines of the Treaty.

The understanding in its entirety was included in the transmittal documents which accompanied the TTB Treaty and the PNE Treaty when they were submitted to the Senate for advice and consent to ratification on July 29, 1976.

Although the TTBT was signed in 1974, it was not sent to the U.S. Senate for advice and consent to ratification until July 1976. Submission was held in abeyance until the companion Treaty on underground nuclear explosions for peaceful purposes (PNET) had been successfully negotiated in accordance with Article III of the TTBT.

For many years, neither the United States nor the Soviet Union ratified the TTBT or the PNE Treaty. However, in 1976 each party separately announced its intention to observe the Treaty limit of 150 kilotons, pending ratification.

The United States and the Soviet Union began negotiations in November 1987 to reach agreement on additional verification provisions that would make it possible for the United States to ratify the treaties. Agreement on additional verification provisions, contained in new protocols, substituting for the original protocols, was reached in June 1990. The TTBT and PNET entered into force on December 11, 1990. The TTBT verification protocol provides for the use of the hydrodynamic yield measurement method with respect to all tests having a planned yield exceeding 50 kilotons, as well as seismic monitoring and, with respect to all tests having a planned yield exceeding 35 kilotons, on-site inspection.


TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE UNION OF SOVIET SOCIALIST REPUBLICS ON THE LIMITATION OF UNDERGROUND NUCLEAR WEAPON TESTS

Signed at Moscow July 3, 1974
Ratified December 8, 1990
Entered into force December 11, 1990

The United States of America and the Union of Soviet Socialist Republics, hereinafter referred to as the Parties,

Declaring their intention to achieve at the earliest possible date the cessation of the nuclear arms race and to take effective measures toward reductions in strategic arms, nuclear disarmament, and general and complete disarmament under strict and effective international control,

Recalling the determination expressed by the Parties to the 1963 Treaty Banning Nuclear Weapon Tests in the Atmosphere, in Outer Space and Under Water in its Preamble to seek to achieve the discontinuance of all test explosions of nuclear weapons for all time, and to continue negotiations to this end,

Noting that the adoption of measures for the further limitation of underground nuclear weapon tests would contribute to the achievement of these objectives and would meet the interests of strengthening peace and the further relaxation of international tension,

Reaffirming their adherence to the objectives and principles of the Treaty Banning Nuclear Weapon Tests in the Atmosphere, in Outer Space and Under Water and of the Treaty on the Non-Proliferation of Nuclear Weapons,

Have agreed as follows: Article I 1. Each Party undertakes to prohibit, to prevent, and not to carry out any underground nuclear weapon test having a yield exceeding 150 kilotons at any place under its jurisdiction or control, beginning March 31, 1976.

2. Each Party shall limit the number of its underground nuclear weapon tests to a minimum.

3. The Parties shall continue their negotiations with a view toward achieving a solution to the problem of the cessation of all underground nuclear weapon tests. Article II 1. For the purpose of providing assurance of compliance with the provisions of this Treaty, each Party shall use national technical means of verification at its disposal in a manner consistent with the generally recognized principles of international law.

2. Each Party undertakes not to interfere with the national technical means of verification of the other Party operating in accordance with paragraph 1 of this Article.

3. To promote the objectives and implementation of the provisions of this Treaty the Parties shall, as necessary, consult with each other, make inquiries and furnish information in response to such inquiries. Article III The provisions of this Treaty do not extend to underground nuclear explosions carried out by the Parties for peaceful purposes. Underground nuclear explosions for peaceful purposes shall be governed by an agreement which is to be negotiated and concluded by the Parties at the earliest possible time. Article IV This Treaty shall be subject to ratification in accordance with the constitutional procedures of each Party. This Treaty shall enter into force on the day of the exchange of instruments of ratification. Article V 1. This Treaty shall remain in force for a period of five years. Unless replaced earlier by an agreement in implementation of the objectives specified in paragraph 3 of Article I of this Treaty, it shall be extended for successive five-year periods unless either Party notifies the other of its termination no later than six months prior to the expiration of the Treaty. Before the expiration of this period the Parties may, as necessary, hold consultations to consider the situation relevant to the substance of this Treaty and to introduce possible amendments to the text of the Treaty.

2. Each Party shall, in exercising its national sovereignty, have the right to withdraw from this Treaty if it decides that extraordinary events related to the subject matter of this Treaty have jeopardized its supreme interests. It shall give notice of its decision to the other Party six months prior to withdrawal from this Treaty. Such notice shall include a statement of the extraordinary events the notifying Party regards as having jeopardized its supreme interests.

3. This Treaty shall be registered pursuant to Article 102 of the Charter of the United Nations.

DONE at Moscow on July 3, 1974, in duplicate, in the English and Russian languages, both texts being equally authentic.

FOR THE UNITED STATES OF AMERICA:
RICHARD NIXON
The President of the United States of America

FOR THE UNION OF SOVIET SOCIALIST REPUBLICS:
L. BREZHNEV
General Secretary of the Central Committee of the CPSU


PROTOCOL TO THE TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE UNION OF SOVIET SOCIALIST REPUBLICS ON THE LIMITATION OF UNDERGROUND NUCLEAR WEAPON TESTS

The United States of America and the Union of Soviet Socialist Republics, hereinafter referred to as the Parties,

Confirming the provisions of the Treaty Between the United States of America and the Union of Soviet Socialist Republics on the Limitation of Underground Nuclear Weapon Tests of July 3, 1974, hereinafter referred to as the Treaty,

Convinced of the necessity to ensure effective verification of compliance with the Treaty,

Have agreed as follows: SECTION I. DEFINITIONS For the purposes of this Protocol:

1. The term "test site" means a geographical area for the conduct of underground nuclear weapon tests, specified in paragraph 1 or in accordance with paragraph 2 of Section II of this Protocol.

2. The term "underground nuclear weapon test," hereinafter "test," means either a single underground nuclear explosion conducted at a test site, or two or more underground nuclear explosions conducted at a test site within an area delineated by a circle having a diameter of two kilometers and conducted within a total period of time of 0.1 second. The yield of a test shall be the aggregate yield of all explosions in the test.

3. The term "explosion" means the release of nuclear energy from an explosive canister.

4. The term "explosive canister" means, with respect to every explosion, the container or covering for one or more nuclear explosives.

5. The term "Testing Party" means the Party conducting a test.

6. The term "Verifying Party" means the Party entitled to carry out, in accordance with this Protocol, activities related to verification of compliance with the Treaty by the Testing Party.

7. The term "Designated Personnel" means personnel appointed by the Verifying Party from among its nationals and included on its list of Designated Personnel, in accordance with Section IX of this Protocol, to carry out activities related to verification in accordance with this Protocol in the territory of the Testing Party.

8. The term "Transport Personnel" means personnel appointed by the Verifying Party from among its nationals and included on its list of Transport Personnel, in accordance with Section IX of this Protocol, to provide transportation for Designated Personnel, their baggage, and equipment of the Verifying Party between the territory of the Verifying Party and the point of entry in the territory of the Testing Party.

9. The term "point of entry" means Washington, D.C. (Dulles International Airport), for Designated Personnel and Transport Personnel, and Travis Air Force Base, California, for Designated Personnel and Transport Personnel and for equipment specified in Section VIII of this Protocol, with respect to the United States of America; and Moscow (Sheremetyevo-2 International Airport) for Designated Personnel and Transport Personnel and for equipment specified in Section VIII of this Protocol, and Leningrad (Pulkovo-2 International Airport) for Designated Personnel and Transport Personnel, with respect to the Union of Soviet Socialist Republics. Other locations may serve as points of entry for specific tests, as agreed by the Parties.

10. The term "hydrodynamic yield measurement method" means the method whereby the yield of a test is derived from on-site, direct measurement of the properties of the shock wave as a function of time during the hydrodynamic phase of the ground motion produced by the test.

11. The term "seismic yield measurement method" means the method whereby the yield of a test is derived from measurement of parameters of elastic ground motion produced by the test.

12. The term "on-site inspection" means activities carried out by the Verifying Party at the test site of the Testing Party, in accordance with Section VII of this Protocol, for the purposes of independently obtaining data on conditions under which the test will be conducted and for confirming the validity of data provided by the Testing Party.

13. The term "emplacement hole" means any drill-hole, shaft, adit or tunnel in which one or more explosive canisters, associated cables, and other equipment are installed for the purposes of conducting a test.

14. The term "end of the emplacement hole" means the reference point established by the Testing Party beyond the planned location of each explosive canister along the axis of the emplacement hole.

15. The term "satellite hole" means any drill-hole, shaft, adit or tunnel in which sensing elements and cables and transducers are installed by the Verifying Party for the purposes of hydrodynamic measurement of the yield of a specific test.

16. The term "standard configuration" means either the standard vertical configuration or the standard horizontal configuration of a test described in paragraph 2 or 3 of Section V of this Protocol.

17. The term "non-standard configuration" means a configuration of a test different from that described in paragraph 2 or 3 of Section V of this Protocol.

18. The term "hydrodynamic measurement zone" means a region, the dimensions of which are specified in paragraph 1 of Section V of this Protocol, within which hydrodynamic yield measurements are carried out.

19. The term "reference test" means a test, identified by the Testing Party as a reference test, that meets the requirements of paragraph 8 of Section V of this Protocol.

20. The term "emplacement point" means the point in the emplacement hole that coincides with the center point of an emplaced explosive canister.

21. The term "choke section" means a barrier designed to restrict the flow of energy from an explosive canister.

22. The term "area of a pipe" or "area of a cableway" means the area of the external cross section of that pipe or cableway measured in a plane perpendicular to the axis of that pipe or cableway at the point within the zone specified in paragraph 2(c), 3(e), or 3(f) of Section V of this Protocol where its cross section is largest.

23. The term "sensing elements and cables" means switches, cables, and cable segments that provide direct measurement of the position of a shock front as a function of time, and are installed in a satellite hole by the Verifying Party for the purposes of use of the hydrodynamic yield measurement method.

24. The term "transducer" means a device that converts physical properties of a shock wave, such as stress and particle velocity, into a recordable signal, and is installed in a satellite hole by the Verifying Party, with associated power supplies, for the purposes of use of the hydrodynamic yield measurement method, with respect to explosions having a planned yield exceeding 50 kilotons and characteristics differing from those set forth in paragraph 2 or 3 of Section V of this Protocol.

25. The term "core sample" means an intact cylindrical sample of geologic material having dimensions no less than two centimeters in diameter and two centimeters in length.

26. The term "rock fragment" means a sample of geologic material having an irregular shape and a volume no less than 10 cubic centimeters.

27. The term "geodetic measurements" means the determination of the geometric position of points within tunnels or cavities.

28. The term "Designated Seismic Station" means any one of the seismic stations designated by each Party, in accordance with Section VI of this Protocol, at which activities related to verification are carried out in accordance with this Protocol.

29. The term "Bilateral Consultative Commission" means the Commission established in accordance with Section XI of this Protocol.

30. The term "Coordinating Group" means a working group of the Bilateral Consultative Commission that is established for each test with respect to which activities related to verification are carried out.

31. The term "coordinated schedule" means the schedule, including the specific times and durations for carrying out activities related to verification for a specific test, established in the Coordinating Group as specified in paragraph 12 of Section XI of this Protocol.

32. The term "Nuclear Risk Reduction Centers" means the Centers located in Washington, D.C., and Moscow, established in accordance with the Agreement Between the United States of America and the Union of Soviet Socialist Republics on the Establishment of Nuclear Risk Reduction Centers of September 15, 1987. SECTION II. TEST SITES 1. The test sites for the Parties are: the Nevada Test Site, for the United States of America; and the Northern Test Site (Novaya Zemlya) and the Semipalatinsk Test Site, for the Union of Soviet Socialist Republics. Upon entry into force of the Treaty, each Party, for each of its test sites, shall provide the other Party with: (a) a precise written description of the boundaries; and (b) a diagram with geographic coordinates of the boundaries to the nearest second, to a scale no smaller than 1:250,000. 2. Following entry into force of the Treaty, if a Party decides to establish a new test site or to change the boundaries of a test site specified in paragraph 1 of this Section, the description and diagram specified in paragraph 1 of this Section shall be transmitted to the other Party no less than 12 months prior to the planned date for conducting the first test at the new test site or area of expansion of a previously specified test site.

3. A test site of a Party shall be located only within its territory. All tests shall be conducted solely within test sites specified in paragraph 1 or in accordance with paragraph 2 of this Section.

4. For the purposes of the Treaty and this Protocol, all underground nuclear explosions at test sites specified in paragraph 1 or in accordance with paragraph 2 of this Section shall be considered underground nuclear weapon tests and shall be subject to all provisions of the Treaty and this Protocol. SECTION III. VERIFICATION MEASURES 1. For purposes of verification of compliance with the Treaty, in addition to using available national technical means, the Verifying Party shall have the right, with respect to tests that are conducted 200 days or more following entry into force of the Treaty: (a) with respect to a test having a planned yield exceeding 50 kilotons, to carry out any or all of the verification activities associated with use of the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, with respect to each explosion in the test; (b) with respect to a test having a planned yield exceeding 50 kilotons, to carry out any or all of the verification activities associated with use of the seismic yield measurement method, in accordance with Section VI of this Protocol; and (c) with respect to a test having a planned yield exceeding 35 kilotons, to carry out any or all of the verification activities associated with on-site inspection, in accordance with Section VII of this Protocol, with respect to each explosion in the test, except that such activities may be carried out with respect to a test having a planned yield exceeding 50 kilotons only if the Verifying Party does not use the hydrodynamic yield measurement method. 2. In addition to the rights specified in paragraph 1 of this Section, for the purposes of building confidence in the implementation of this Protocol and improving its national technical means of verification, the Verifying Party shall have the right: (a) if, in each of the five calendar years immediately following entry into force of the Treaty, the Testing Party does not conduct at least two tests having a planned yield exceeding 50 kilotons, to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, with respect to two tests from among those having the highest planned yields that the Testing Party conducts in that calendar year; (b) if, in the sixth calendar year following entry into force of the Treaty and in each calendar year thereafter, unless the Parties otherwise agree, the Testing Party does not conduct at least one test having a planned yield exceeding 50 kilotons, to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, with respect to one test from among those having the highest planned yield that the Testing Party conducts in that calendar year; (c) if, in any calendar year, the Testing Party postpones a test having a planned yield of 50 kilotons or less to the following calendar year, after having been notified by the Verifying Party of its intent to use the hydrodynamic yield measurement method with respect to that test, to use such method with respect to that test in the following calendar year. This right shall be additional to the rights specified in paragraph 1(a) of this Section and in subparagraphs (a) and (b) of this paragraph; and (d) in addition to the rights specified in subparagraphs (a), (b), and (c) of this paragraph, if, in each of the five calendar years beginning with the conduct of the first test by the Testing Party at a new test site, the Testing Party does not conduct at least two tests having a planned yield exceeding 50 kilotons at the new test site, the Verifying Party shall have the right to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, with respect to two tests from among those having the highest planned yields that the Testing Party conducts at the new test site in that calendar year. 3. If the Verifying Party has notified the Testing Party that it intends to use the hydrodynamic yield measurement method with respect to a specific test including more than one explosion, unless the Parties agree on verification measures with respect to such a test: (a) the distance between the closest points of any two adjacent explosive canisters shall be no less than 50 meters; and (b) the time of each explosion shall be established by the Testing Party so as to permit the carrying out of hydrodynamic yield measurements for each explosion for a distance of no less than 30 meters in the satellite hole closest to the emplacement hole with which it is associated. 4. If the Verifying Party has notified the Testing Party that it intends to use the hydrodynamic yield measurement method with respect to a specific test, and if that test is conducted in more than one emplacement hole, the Testing Party shall have the right to conduct that test only if no more than one emplacement hole has characteristics or contains explosive canisters having characteristics differing from those set forth in paragraph 2 or 3 of Section V of this Protocol with respect to a test of standard configuration, unless the Parties agree on verification measures with respect to such a test.

5. The Testing Party shall have the right to conduct a test having a planned yield exceeding 35 kilotons within a time period of less than two seconds of any other test having a planned yield exceeding 35 kilotons only if the Parties agree on verification measures with respect to such tests. No test shall be conducted within 15 minutes prior to or following a reference test, unless the Parties otherwise agree.

6. The Testing Party shall have the right to conduct a test having a planned yield exceeding 35 kilotons in a cavity having a volume exceeding 20,000 cubic meters only if the Parties agree on verification measures with respect to such a test.

7. The Verifying Party, by notifying the Testing Party that it intends to use the hydrodynamic yield measurement method with respect to a test of non-standard configuration having a planned yield exceeding 50 kilotons, shall have the right to require a reference test for this non-standard test, in order to compare the yields measured through its national technical means for these two associated tests with the yield obtained by carrying out hydrodynamic yield measurement of the reference test. The right of the Verifying Party to a reference test shall be independent of whether or not it actually carries out hydrodynamic yield measurements of the test of non-standard configuration.

8. With respect to the requirement for a reference test: (a) if the Testing Party, at the time it provides notification of a test, identifies that test as a reference test for a future test of non-standard configuration, and if the Verifying Party does not use the hydrodynamic yield measurement method with respect to the identified reference test, the Verifying Party shall forfeit its right to require a reference test for that test of non-standard configuration and for any subsequent test of non-standard configuration that would be associated with that reference test, if the Testing Party conducts the identified reference test; (b) the Testing Party shall have the right to identify only one test>


Transfer interrupted!

ence test not associated with any specific test of non-standard configuration until it has conducted an associated test of non-standard configuration for which this test serves as a reference test, or unless it simultaneously provides notification of the associated test of non-standard configuration; and (c) if the Testing Party, at the time it provides notification of a test of standard configuration, indicates that the test will satisfy a requirement for a reference test for a previously conducted test of non-standard configuration, and if the Verifying Party notifies the Testing Party of its intent not to use the hydrodynamic yield measurement method with respect to that reference test, the Verifying Party shall forfeit its right to require a reference test for the previously conducted test of non-standard configuration. In that case, the Testing Party shall have the right to cancel that reference test. 9. Following notification by the Verifying Party, in accordance with paragraph 5 of Section IV of this Protocol, of whether or not it intends to carry out any of the activities related to verification for a specific test, and, if so, which activities, the Verifying Party shall forfeit its right to revise that notification unless the Testing Party changes the previously declared location of that test by more than one minute of latitude or longitude or changes the planned yield of a test from 50 kilotons or less to a planned yield exceeding 50 kilotons. If the Testing Party makes any such change, the Verifying Party shall have the right to revise its previous notification and to carry out any of the activities specified in paragraph 1 or 2 of this Section and, if the Verifying Party notifies the Testing Party that it intends to carry out activities related to verification with respect to that test, in accordance with paragraph 20 of Section IV of this Protocol, the Testing Party shall not conduct the test less than 180 days following the date of the revised notification by the Verifying Party, unless the Parties otherwise agree.

10. Designated Personnel shall have the right to carry out activities related to verification in accordance with this Protocol, 24 hours a day, provided such activities are consistent with the safety requirements of the Testing Party at the test site or Designated Seismic Station. All operations and procedures that require the participation of Designated Personnel and personnel of the Testing Party shall be carried out in accordance with the technical operations and practices at the test site or Designated Seismic Station of the Testing Party, and in this connection:

(a) Designated Personnel:
(i) shall not interfere with activities of personnel of the Testing Party at the test site or Designated Seismic Station; and

(ii) shall be responsible for the working of their equipment, its timely installation and operation, participation in such operations, including dry runs, as the Testing Party may request, and recording of data; and

(b) the Testing Party:
(i) shall be under no obligation to delay the test because of any malfunction of the equipment of the Verifying Party or inability of Designated Personnel to carry out their functions, unless the Testing Party caused such a situation to arise; and

(ii) shall bear full responsibility for the preparation and conduct of the test and shall have exclusive control over it.

11. If the Verifying Party has notified the Testing Party that it intends to carry out activities related to verification for a specific test, the Testing Party shall have the right to make changes in the timing of its operations related to the conduct of that test, except that the Testing Party shall not make changes in the timing of its operations related to the conduct of that test that would preclude Designated Personnel from carrying out their rights related to verification provided in this Protocol. If the Testing Party notifies the Verifying Party of a change in the timing of its operations that the Verifying Party deems would either preclude or significantly limit the exercise of such rights, the Coordinating Group shall meet at the request of the Representative of the Verifying Party to the Coordinating Group, to consider the change in order to ensure that the rights of the Verifying Party are preserved. If the Coordinating Group cannot agree on a revision to the coordinated schedule that will ensure the rights of both Parties as provided in this Protocol, there shall be no advancement of events within the coordinated schedule due to such a change. Either Party may request that the Bilateral Consultative Commission consider any such change in timing of operations or in the coordinated schedule, in accordance with paragraph 15 of Section XI of this Protocol. SECTION IV. NOTIFICATIONS AND INFORMATION RELATING TO TESTS 1. Unless otherwise provided in this Protocol, all notifications required by this Protocol shall be transmitted through the Nuclear Risk Reduction Centers. The Nuclear Risk Reduction Centers may also be used, as appropriate, to transmit other information provided in accordance with this Protocol.

2. Not later than the June 1 immediately following entry into force of the Treaty, and not later than June l of each year thereafter, each Party shall provide the other Party with the following information on tests that it intends to conduct in the following calendar year:

(a) the projected number of tests having a planned yield exceeding 35 kilotons;

(b) the projected number of tests having a planned yield exceeding 50 kilotons; and

(c) if the number of tests declared in accordance with subparagraphs (a) and (b) of this paragraph is less than the number of tests for which rights are specified in paragraph 2 of Section III of this Protocol, whether it intends to conduct a sufficient number of other tests to permit the Verifying Party to exercise fully the rights specified in paragraph 2 of Section III of this Protocol.

3. On the date of entry into force of the Treaty each Party shall provide the other Party with the information specified in paragraphs 2(a) and 2(b) of this Section for the remainder of the calendar year in which the Treaty enters into force, and, if the Treaty enters into force after June 1, information specified in paragraph 2 of this Section for the following calendar year.

4. No less than 200 days prior to the planned date of any test with respect to which the Verifying Party has the right to carry out any activity related to verification in accordance with this Protocol, the Testing Party shall provide the Verifying Party with the following information to the extent and degree of accuracy available at that time:

(a) the planned date of the test and its designation;

(b) the planned date of the beginning of emplacement of explosive canisters;

(c) the location of the test, expressed in geographic coordinates to the nearest minute;

(d) whether the planned yield of the test exceeds 35 kilotons;

(e) whether the planned yield of the test exceeds 50 kilotons;

(f) if the planned yield is 50 kilotons or less, whether the test is one of the tests with respect to which the Verifying Party has the right to use the hydrodynamic yield measurement method, in accordance with paragraph 2 of Section III of this Protocol;

(g) the planned depth of each emplacement hole to the nearest 10 meters;

(h) the type or types of rock in which the test will be conducted, including the depth of the water table;

(i) whether the test will be of standard or non-standard configuration; and

(j) whether the test will serve as a reference test for:

(i) a previously conducted test of non-standard configuration with which such a reference test is associated;

(ii) a future test of non-standard configuration for which notification has been provided or is being simultaneously provided in accordance with paragraph 8(b) of Section III of this Protocol; or

(iii) a future test of non-standard configuration for which the Testing Party has not yet provided notification.

5. Within 20 days following receipt of information specified in paragraph 4 of this Section, the Verifying Party shall inform the Testing Party, in a single notification, whether or not it intends to carry out, with respect to this test, any activities related to verification that it has a right to carry out, in accordance with Section III of this Protocol, and, if so, whether it intends:
(a) to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol;

(b) to use the seismic yield measurement method, in accordance with Section VI of this Protocol; and

(c) to carry out on-site inspection, in accordance with Section VII of this Protocol.

6. Within 30 days following notification by the Verifying Party, in accordance with paragraph 11 of Section XI of this Protocol, that it requires a reference test for a test of non-standard configuration, the Testing Party shall notify the Verifying Party whether it will meet the requirement for a reference test through:
(a) the identification of a previously conducted reference test;

(b) the identification of a previously conducted test of standard configuration, meeting the requirements for a reference test, with respect to which the Verifying Party carried out hydrodynamic yield measurements;

(c) the identification of a previously notified test of standard configuration, meeting the requirements for a reference test, with respect to which the Verifying Party has notified the Testing Party of its intent to carry out hydrodynamic yield measurements; or

(d) the conduct of a reference test within 12 months of the non-standard test, whose identification as a reference test will be made in the notification, in accordance with paragraph 4(j) of this Section.

7. If the Verifying Party notifies the Testing Party that it intends to use the hydrodynamic yield measurement method, the Testing Party shall provide the Verifying Party, no less than 120 days prior to the planned date of the test, with the following information:
(a) a description of the geological and geophysical characteristics of the test location, which shall include: the depth of the water table; the stratigraphic column, including the lithologic description of each formation; the estimated physical parameters of the rock, including bulk density, grain density, compressional velocity, porosity, and total water content; and information on any known geophysical discontinuities in the media within each hydrodynamic measurement zone;

(b) the planned cross-sectional dimensions of each emplacement hole in each hydrodynamic measurement zone;

(c) the location and configuration of any known voids larger than one cubic meter within each hydrodynamic measurement zone;

(d) a description of materials, including their densities, to be used to stem each emplacement hole within each hydrodynamic measurement zone;

(e) whether it is planned that each emplacement hole will be fully or partially cased, and, if so, a description of materials of this casing;

(f) whether it is planned that each satellite hole will be fully or partially cased, and, if so, a description of materials of this casing;

(g) a topographic map to a scale no smaller than 1:25,000 and a contour interval of 10 meters or less showing:

(i) an area with a radius of no less than two kilometers centered on the entrance to each emplacement hole, that shall include the area delineated by a circle having a radius of 300 meters centered directly above the planned emplacement point of each explosive canister; and

(ii) a one-kilometer wide corridor centered on the planned location of the above-ground cables of the Verifying Party;

(h) overall drawings showing the external dimensions of each explosive canister and each choke section, and any pipes or cableways passing through a choke section, as well as any other pipes and cableways connected to that explosive canister and located within five meters of that explosive canister;

(i) the specific locations, referenced to the entrance to each vertical satellite hole or to the surface location of the entrance to each horizontal emplacement hole, at which individual gas-blocking devices shall be installed if such devices are used on the electrical cables specified in paragraphs 3(a) and 3(b) of Section VIII of this Protocol; and

(j) whether the Testing Party will provide satellite communications as specified in paragraph 13 of Section X of this Protocol for use by Designated Personnel.

8. If the Verifying Party notifies the Testing Party that it intends to use the seismic yield measurement method, the Testing Party shall provide the Verifying Party, no less than 120 days prior to the planned date of the test, with the information specified in paragraphs 9(a), 9(b), and 9(c) of this Section.

9. If the Verifying Party notifies the Testing Party that it intends to carry out on-site inspection, the Testing Party shall provide the Verifying Party, no less than 120 days prior to the planned date of the test, with the following information:

(a) a description of the geological and geophysical characteristics of the test location, which shall include: the depth of the water table; the stratigraphic column, including the lithologic description of each formation; the estimated physical parameters of the rock, including bulk density, grain density, compressional velocity, porosity, and total water content; and information on any known geophysical discontinuities in the media within a radius of 300 meters of the planned emplacement point of each explosive canister;

(b) the planned cross-sectional dimensions of each emplacement hole in the portion within 300 meters of the planned emplacement point of each explosive canister;

(c) the location and configuration of any known voids larger than 1000 cubic meters within a radius of 300 meters of the planned emplacement point of each explosive canister;

(d) whether it is planned that each emplacement hole will be fully or partially cased, and, if so, a description of materials of this casing;

(e) a topographic map to a scale no smaller than 1:25,000 and a contour interval of 10 meters or less showing an area with a radius of no less than two kilometers centered on the entrance to each emplacement hole, that shall include the area delineated by a circle having a radius of 300 meters centered directly above the planned emplacement point of each explosive canister; and

(f) whether the Testing Party will provide satellite communications as specified in paragraph 13 of Section X of this Protocol for use by Designated Personnel.

10. The Testing Party shall immediately notify the Verifying Party of any change in any information provided in accordance with paragraph 2, 3, 4(a), 4(c), 4(d), 4(e), 4(f) or 4(j) of this Section, and:
(a) if the Verifying Party has notified the Testing Party that it intends to carry out activities related to verification in accordance with Section V of this Protocol, of any change in any information provided in accordance with paragraph 4(b), 4(g), 4(h), 4(i), 6 or 7 of this Section, or paragraph 10 of Section XI of this Protocol;

(b) if the Verifying Party has notified the Testing Party that it intends to carry out activities related to verification in accordance with Section VI of this Protocol, of any change in any information provided in accordance with paragraph 4(g), 4(h) or 8 of this Section; and

(c) if the Verifying Party has notified the Testing Party that it intends to carry out activities related to verification in accordance with Section VII of this Protocol, of any change in any information provided in accordance with paragraph 4(b), 4(g), 4(h) or 9 of this Section, or paragraph 10(a) of Section XI of this Protocol.

11. If the Testing Party makes changes in the information specified in paragraph 4(a), 10(a), 10(b) or 10(c) of this Section related to a specific test for which Designated Personnel are present in the territory of the Testing Party, it shall also immediately notify, in writing, the Designated Personnel Team Leader carrying out activities related to verification of that test at the test site and at each Designated Seismic Station of such changes.

12. The Testing Party shall immediately inform the Verifying Party of any change in the timing of its operations related to the conduct of a specific test that affects the coordinated schedule, and if Designated Personnel are present in the territory of the Testing Party, it shall also immediately notify, in writing, the Designated Personnel Team Leader carrying out activities related to verification of that test at the test site and at each Designated Seismic Station.

13. If, in carrying out activities related to verification of a specific test, Designated Personnel are present at the test site or any Designated Seismic Station:

(a) no less than 48 hours prior to the initial planned time of the test, the Testing Party shall notify each Designated Personnel Team Leader, in writing, of the time for beginning the period of readiness for the test and the planned time of the test, to the nearest second. This and all subsequent notifications shall be referenced to Universal Time Coordinated and to local time at the test site or the Designated Seismic Station;

(b) except as otherwise provided in this Section, if the Testing Party changes the planned time of the test, it shall immediately notify each Designated Personnel Team Leader, in writing, of the new planned time of the test;

(c) the Testing Party shall conduct the test only within a period of readiness;

(d) unless the Parties otherwise agree, the period of readiness shall begin:

(i) no less than six days following completion of stemming of the hydrodynamic measurement zone of all satellite holes, if verification activities in accordance with Section V of this Protocol are carried out; and

(ii) no more than five days prior to the planned date of the test, if verification activities in accordance with Section VI of this Protocol are carried out;

(e) the Testing Party may terminate the period of readiness at any time. The Testing Party shall then immediately notify each Designated Personnel Team Leader, in writing, that the period of readiness has been terminated; and

(f) if the Testing Party terminates the period of readiness or changes the time for beginning the period of readiness, it shall provide notice of the time for beginning a new period of readiness to each Designated Personnel Team Leader, in writing, no less than 12 hours prior to beginning this new period of readiness.

14. Following notification in accordance with paragraph 13(a) or 13(b) of this Section, the Testing Party, without further notification, may advance the time of the test by no more than five minutes.

15. After the event readiness signal specified in paragraph 10(b) of Section V of this Protocol has been started:

(a) if the Testing Party delays the test and terminates the event readiness signal at least one second prior to the planned time of the test, it may carry out the test, without further notification, at any time within no more than 60 minutes after the planned time of the test, provided it generates a new event readiness signal; and

(b) if the Testing Party subsequently delays the test without ending the event readiness signal at least one second prior to the planned time of the test, the Testing Party shall end the event readiness signal and shall not begin a new event readiness signal within 20 minutes following that planned time of the test. The Testing Party shall notify each Designated Personnel Team Leader, in writing, of the new planned time of the test, at least 10 minutes prior to the beginning of the new event readiness signal for that test.

16. Following notification in accordance with paragraph 13(a) or 13(b) of this Section, if the test is delayed by more than 60 minutes the Testing Party shall notify each Designated Personnel Team Leader, in writing, of the new planned time of the test no less than 30 minutes prior to the new planned time of the test.

17. During the period of readiness, if a test is delayed by more than three hours from the last notification of the planned time of the test, the Testing Party shall notify each Designated Personnel Team Leader, in writing, of the period during which the test will not be conducted.

18. No less than one hour following the test, the Testing Party shall notify each Designated Personnel Team Leader, in writing, of the actual time of the test to the nearest 0.1 second.

19. For each test for which notification has been provided in accordance with paragraph 4 of this Section, no less than 48 hours prior to the initial planned time of the test, the Testing Party shall notify the Verifying Party of the planned time of the test to the nearest one second. If the Testing Party subsequently delays the planned time of the test by more than 24 hours, it shall immediately notify the Verifying Party of the new planned time of the test to the nearest one second. No less than three days following the test, the Testing Party shall notify the Verifying Party of the actual time of the test, referenced to Universal Time Coordinated, to the nearest 0.1 second.

20. The Testing Party shall immediately notify the Verifying Party of a change in the location of a test by more than one minute of latitude or longitude or of a change in the planned yield of a test from 50 kilotons or less to a planned yield exceeding 50 kilotons. The Verifying Party shall notify the Testing Party, within 20 days following receipt of notification of such a change in the location or planned yield of the test, whether it intends to carry out for this test any activities related to verification in accordance with paragraph 9 of Section III of this Protocol. If the Verifying Party, in this revised notification, notifies the Testing Party that it intends to carry out any of the activities related to verification that it has a right to carry out in accordance with Section III of this Protocol, the Testing Party shall provide the Verifying Party with the information that it is required to provide in accordance with paragraphs 7, 8, and 9 of this Section and paragraph 10 of Section XI of this Protocol.

21. If the Verifying Party has notified the Testing Party that it intends to use the hydrodynamic yield measurement method, the beginning of emplacement of sensing elements and cables shall not occur less than 90 days after notification of any change in the location of the test by more than one minute of latitude or longitude, unless the Parties otherwise agree.

22. If the Verifying Party has notified the Testing Party that it does not intend to carry out hydrodynamic yield measurements for a specific test, the Testing Party shall have the right to change the configuration of that test from standard to non-standard or vice versa, without notifying the Verifying Party of such change.

23. If the Verifying Party has notified the Testing Party that it intends to carry out hydrodynamic yield measurements for a specific test, the Testing Party shall immediately notify the Verifying Party of a change in the configuration of that test from standard to non-standard, or vice versa, or of any increase in the number of emplacement holes or explosive canisters of the test. The Verifying Party shall, within five days of notification of any such change, notify the Testing Party whether it will revise its initial notification and whether it deems that this change would either preclude or significantly limit the exercise of its rights provided in this Protocol. If so, the Coordinating Group shall immediately meet to consider a revision in the coordinated schedule that will ensure the rights of both Parties provided in this Protocol. If the Parties cannot agree on a revised coordinated schedule within 15 days following notification by the Testing Party of such a change, the date of notification of the change shall be deemed the initial notification of a test in accordance with paragraph 4 of this Section, and the test shall be conducted no less than 180 days following the date of notification of the change.

24. If the Verifying Party has notified the Testing Party that it intends to carry out on-site inspection with respect to a specific test, and if the Testing Party notifies the Verifying Party of an increase in the number of explosive canisters or an increase in the number of emplacement holes, the Verifying Party shall, within five days of notification of any such change, notify the Testing Party whether it deems that this change would significantly limit the exercise of its rights provided in this Protocol. If so, the Coordinating Group shall immediately meet to consider a revision in the coordinated schedule that will ensure the rights of both Parties provided in this Protocol. If the Parties cannot agree on a revised coordinated schedule within 15 days following notification by the Verifying Party that it deems that, as a result of such an increase, its rights would be significantly limited, the date of that notification shall be deemed notification by the Verifying Party that it intends to carry out on-site inspection in accordance with paragraph 5 of this Section, and the test shall be conducted no less than 165 days following the date of such notification.

25. The Verifying Party may at any time, but no later than one year following the test, request from the Testing Party clarification of any point of information provided in accordance with this Section. Such clarification shall be provided in the shortest possible time, but no later than 30 days following receipt of the request. SECTION V. HYDRODYNAMIC YIELD MEASUREMENT METHOD 1. The hydrodynamic measurement zone is:

(a) with respect to a test of standard configuration, described in paragraph 2 or 3 of this Section, as well as with respect to any explosion having a planned yield of 50 kilotons or less:
(i) if an emplacement hole is vertical, the cylindrical region 25 meters in diameter whose axis is midway between the axes of the emplacement hole and the satellite hole, extending from a point 30 meters below the end of the emplacement hole to a point 100 meters from the end of the emplacement hole in the direction of the entrance to the emplacement hole; or

(ii) if an emplacement hole is horizontal, the cylindrical region 25 meters in diameter whose axis is midway between the axes of the emplacement hole and the satellite hole, extending from a point 15 meters beyond the end of the emplacement hole to a point 65 meters from the end of the emplacement hole in the direction of the entrance to the emplacement hole; and

(b) with respect to a test of non-standard configuration having a planned yield exceeding 50 kilotons:
(i) if an emplacement hole is vertical, the cylindrical region 200 meters in diameter coaxial with the emplacement hole, extending from a point 30 meters below the end of the emplacement hole to a point 100 meters from the center point of the explosive canister in the direction of the entrance to the emplacement hole; or

(ii) if an emplacement hole is horizontal, the cylindrical region 130 meters in diameter whose axis is coaxial with the emplacement hole, extending from a point 15 meters beyond the end of the emplacement hole to a point 65 meters from the center point of the explosive canister in the direction of the entrance to the emplacement hole.

2. For the purposes of the use of the hydrodynamic yield measurement method, a test shall be deemed of standard vertical configuration if:
(a) each emplacement hole is vertical and cylindrical, and is drilled or excavated with a diameter no greater than four meters;

(b) the bottom of each emplacement hole is filled with stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock, to form a plug no less than three meters thick, and the top of this plug of stemming material is the end of the emplacement hole for the explosive canister emplaced farthest from the entrance to the emplacement hole;

(c) any pipe or cableway connected to an explosive canister passes through a choke section. This choke section is installed on the top of the explosive canister and has the following characteristics:

(i) the diameter of the choke section is no less than that of the explosive canister;

(ii) the choke section is no less than one meter thick;

(iii) the sum of the areas of all pipes and cableways within the choke section does not exceed 0.5 square meters;

(iv) the area of each pipe or cableway within the choke section does not exceed 0.3 square meters;

(v) the part of the choke section in contact with the explosive canister consists of a steel plate having a thickness no less than 0.005 meters; and

(vi) the choke section, except for pipes and cableways, is filled, prior to emplacement, with stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock, and has a product of density and thickness no less than 250 grams per square centimeter;

(d) the length of each explosive canister does not exceed 12 meters and, after an explosive canister is emplaced, the lowest part of the choke section is no more than 12 meters above the end of the emplacement hole;

(e) the diameter of each explosive canister does not exceed three meters;

(f) each emplacement hole has been drilled or excavated with a diameter, within each hydrodynamic measurement zone, no more than one meter greater than the diameter of each explosive canister; or, if an emplacement hole has been cased, the inside diameter of the casing, within each hydrodynamic measurement zone, is no more than one meter greater than the diameter of each explosive canister. Within the 15-meter segment above the end of each emplacement hole for each explosive canister, no washouts penetrate more than one meter into the wall of the emplacement hole;

(g) all voids in or connected to an emplacement hole, within each hydrodynamic measurement zone, external to:

(i) any explosive canister;

(ii) any choke sections;

(iii) any diagnostic canisters; and

(iv) associated cables and pipes

are filled with stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock;

(h) within each hydrodynamic measurement zone, all voids greater than 10 cubic meters, external and unconnected to an emplacement hole or a satellite hole, and all voids greater than one cubic meter, within two meters of the wall of a satellite hole or any part of an explosive canister, are filled with stemming material having a bulk density no less than 70 percent of the average density of the surrounding rock; and

(i) within each hydrodynamic measurement zone, the distance between a satellite hole and any other drilled hole or excavation is no less than the distance between that satellite hole and the emplacement hole with which it is associated.

3. For the purposes of the use of the hydrodynamic yield measurement method, a test shall be deemed of standard horizontal configuration if:
(a) each emplacement hole is horizontal, with an excavated cross section, measured in the plane perpendicular to its axis, no greater than five meters by five meters for the first 65 meters from the end of the emplacement hole for each explosive canister, except that any diagnostic canister associated with it shall occupy, in an emplacement hole, space having a cross section no greater than 3.5 meters by 3.5 meters for the first 50 meters of the emplacement hole from the choke section of each explosive canister in the direction of the entrance to the emplacement hole;

(b) the end of each emplacement hole is either:

(i) unsupported native rock, the surface of which is essentially perpendicular to the axis of the emplacement hole; or

(ii) the surface of a plug no less than three meters thick, formed of stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock;

(c) the length of each explosive canister does not exceed 12 meters and, after it is emplaced, the end of the explosive canister farthest from the entrance to the emplacement hole is no less than one meter and no more than two meters from the end of the emplacement hole;

(d) the cross section of each explosive canister measured in the plane perpendicular to the axis of the emplacement hole does not exceed three meters by three meters;

(e) any pipe or cableway connected to an explosive canister and lying entirely within the emplacement hole passes through a choke section. This choke section is installed at the end of the explosive canister nearest to the entrance of the emplacement hole and has the following characteristics:

(i) the dimensions of the choke section perpendicular to the axis of the emplacement hole are no less than those of the explosive canister;

(ii) the choke section is no less than one meter thick;

(iii) the sum of the areas of all pipes and cableways within the choke section, plus the sum of the areas of pipes and cableways specified in subparagraph (f) of this paragraph, does not exceed 0.5 square meters;

(iv) the area of each pipe or cableway within the choke section does not exceed 0.3 square meters; and

(v) the choke section, except for pipes and cableways meeting the requirements of subparagraphs (e)(iii) and (e)(iv) of this paragraph, is filled with stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock, and has a product of density and thickness no less than 250 grams per square centimeter;

(f) any pipe or cableway connected to any surface of an explosive canister and not lying entirely within the emplacement hole has the following characteristics:
(i) the area of each pipe or cableway within five meters of the explosive canister does not exceed 0.05 square meters; and

(ii) the sum of the areas of all such pipes and cableways within five meters of the explosive canister does not exceed 0.1 square meters;

(g) any diagnostic canister connected to the pipes or cableways specified in subparagraph (f) of this paragraph lies entirely outside the hydrodynamic measurement zone;

(h) all voids in or connected to an emplacement hole, including any bypass or access tunnels within the hydrodynamic measurement zone, external to:

(i) any explosive canister;

(ii) any choke sections;

(iii) any diagnostic canisters; and

(iv) associated cables and pipes

are filled with stemming material having a bulk density no less than 60 percent of the average density of the surrounding rock;

(i) within each hydrodynamic measurement zone, all voids greater than 10 cubic meters, external and unconnected to an emplacement hole or a satellite hole, and all voids greater than one cubic meter, within two meters of the wall of a satellite hole or any part of an explosive canister, are filled with stemming material having a bulk density no less than 70 percent of the average density of the surrounding rock; and

(j) within the portion of each hydrodynamic measurement zone extending from the end of the emplacement hole in the direction of the entrance to the emplacement hole, the distance between a satellite hole and any other tunnel or excavation is no less than the distance between that satellite hole and the emplacement hole with which it is associated.

4. With respect to a test of standard configuration, as well as with respect to any explosion having a planned yield of 50 kilotons or less:
(a) personnel of the Testing Party, using their own equipment, shall drill or excavate a satellite hole associated with each emplacement hole, at a time of their own choosing. The Testing Party shall have the right to complete drilling or excavation of a satellite hole for a specific test prior to the arrival of Designated Personnel at the test site to carry out activities related to use of the hydrodynamic yield measurement method for that test. Each satellite hole shall meet the following requirements:
(i) if an emplacement hole is vertical, the axis of the associated satellite hole shall be located 11 meters, plus or minus three meters, from the axis of the emplacement hole within each hydrodynamic measurement zone. If an emplacement hole is horizontal, the axis of the associated satellite hole shall be located 11 meters, plus or minus two meters, from the axis of the emplacement hole within each hydrodynamic measurement zone, and it may be drilled or excavated either as a single continuous hole or in separate consecutive segments associated with each hydrodynamic measurement zone. The axis of any satellite hole shall be no less than six meters from the wall of any drilled or excavated cavity or hole;

(ii) its end shall be no less than 30 meters below the level of the end of the associated vertical emplacement hole farthest from the entrance to the emplacement hole, or no less than 15 meters beyond the point at which the satellite hole is closest to the end of the associated horizontal emplacement hole farthest from the entrance to the emplacement hole;

(iii) if it is prepared by drilling, it shall be drilled no less than 0.3 meters and no more than 0.5 meters in diameter. Within each hydrodynamic measurement zone, no washouts shall penetrate more than one meter into the wall of the hole; and

(iv) if it is prepared by excavation, it shall have an excavated cross section, measured in the plane perpendicular to its axis, no greater than 2.5 meters by 2.5 meters within each hydrodynamic measurement zone;

(b) Designated Personnel shall have the right to observe the activities of the personnel of the Testing Party carried out to meet the specifications set forth in paragraph 2(b) of this Section and, if applicable, set forth in paragraph 3(b)(ii) of this Section. A representative sample of no less than 1000 cubic centimeters in volume of the stemming material used to form the plugs specified in paragraphs 2(b) and 3(b)(ii) of this Section shall be provided to Designated Personnel for retention;

(c) Designated Personnel shall have the right to carry out, under observation of personnel of the Testing Party and with their assistance, if such assistance is requested by Designated Personnel, directional surveys and geodetic measurements of each satellite hole and emplacement hole prior to the planned date of the beginning of emplacement of sensing elements and cables;

(d) equipment specified in paragraph 3 of Section VIII of this Protocol shall be operated by Designated Personnel and shall be installed, in accordance with installation instructions provided in accordance with paragraph 6(c) of Section VIII of this Protocol, by Designated Personnel under observation of personnel of the Testing Party and with their assistance, if such assistance is requested by Designated Personnel. The location of each hydrodynamic recording facility and the command and monitoring facility of the Verifying Party and the instrumentation facility of the Testing Party specified in paragraph 10(l) of this Section shall be determined by the Testing Party in consultation with the Verifying Party in the Coordinating Group no less than 90 days prior to the beginning of emplacement of sensing elements and cables. Areas for the installation of these facilities, cable supports, and cableways for protection of cables of the Verifying Party, specified in paragraphs 3(b), 3(f), and 3(g) of Section VIII of this Protocol, shall be prepared by the Testing Party in accordance with requirements agreed upon in the Coordinating Group. Only cables of the Verifying Party shall be installed in these cableways. Designated Personnel shall have access, under observation of personnel of the Testing Party, to the cables specified in paragraphs 3(f) and 3(g) of Section VIII of this Protocol and to the cableways in which they are installed, at all times. Personnel of the Testing Party shall have access to these cableways only under observation of Designated Personnel;

(e) Designated Personnel shall have the right to use their own primary electrical power sources to supply electrical power to hydrodynamic equipment specified in paragraph 3 of Section VIII of this Protocol. At the request of the Verifying Party, the Testing Party shall supply electrical power from the standard electrical network of its test site through converters provided by the Verifying Party or, by agreement of the Parties, by the Testing Party;

(f) for each test, the only equipment installed in a satellite hole shall be that of the Verifying Party specified in paragraphs 3(a) and 3(h) of Section VIII of this Protocol. If an emplacement hole is vertical, the end point of the equipment farthest from the entrance to the satellite hole shall be installed no less than 30 meters below the level of the end of the emplacement hole farthest from the entrance to the emplacement hole. If an emplacement hole is horizontal, the end point of this equipment shall be installed no less than 15 meters beyond the point at which a satellite hole is closest to the end of the emplacement hole farthest from the entrance to the emplacement hole. For each satellite hole, Designated Personnel shall have the right to install no more than six sensing elements and cables, without regard to the number of switches. Personnel of each Party shall have the right to measure the location of the installed sensing elements and cables;

(g) Designated Personnel shall have the right to conduct a final directional survey and geodetic measurements of each satellite hole upon completion of installation of sensing elements and cables;

(h) personnel of the Testing Party, under observation of Designated Personnel, shall fill all voids in or connected to each satellite hole within each hydrodynamic measurement zone with a stemming material agreed upon by the Parties, having a bulk density no less than 70 percent of the average density of the surrounding rock. A representative sample of no less than 1000 cubic centimeters in volume of each stemming material used in each hydrodynamic measurement zone shall be provided to Designated Personnel for retention. The methods and materials used for stemming satellite holes and any hydrodynamic measurement equipment emplacement pipe shall:

(i) be consistent with the containment practices of the Testing Party;

(ii) be chosen to minimize voids around sensing elements and cables; and

(iii) be chosen to avoid damage to the sensing elements and cables;

(i) Designated Personnel shall have the right to observe the stemming of the hydrodynamic measurement zones of each emplacement hole in accordance with paragraphs 2(g) and 3(h) of this Section. A representative sample of no less than 1000 cubic centimeters in volume of each stemming material used in each hydrodynamic measurement zone shall be provided to Designated Personnel for retention;

(j) the Testing Party shall have the right to case or line each emplacement hole; and

(k) the Testing Party shall have the right to case or line each satellite hole, provided that:

(i) sensing elements and cables can be installed as specified in subparagraph (f) of this paragraph;

(ii) casing or lining material in each hydrodynamic measurement zone is agreed upon by the Parties; and

(iii) casing or lining in each hydrodynamic measurement zone is affixed to the surrounding formation with material agreed upon by the Parties.

5. In preparation for the use of the hydrodynamic yield measurement method with respect to a test of standard configuration, as well as with respect to any explosion having a planned yield of 50 kilotons or less:
(a) upon their arrival at the test site, no less than 10 days prior to the planned date of the beginning of emplacement of sensing elements and cables, Designated Personnel shall provide the Testing Party with a description of the recording format and the computer program, to enable the Testing Party to read digital data if digital recordings of hydrodynamic data will be made by Designated Personnel;

(b) the Testing Party shall provide Designated Personnel upon their arrival at the test site with the results of any studies of core samples and rock fragments extracted from each emplacement hole and satellite hole and any exploratory holes and tunnels, and the results of logging and geodetic measurements carried out in each emplacement hole, each satellite hole, and any exploratory holes and tunnels, relevant to the geology and geophysics of each hydrodynamic measurement zone, if the Testing Party carried out such studies and measurements;

(c) using their own equipment and under observation of personnel of the Testing Party, Designated Personnel shall have the right to carry out:

(i) if an emplacement hole is vertical, in the emplacement hole and associated satellite hole, caliper logs, directional surveys, geodetic measurements, and depth or distance measurements to determine the dimensions and the relative locations of the emplacement hole and satellite hole, as well as measurements to determine the location and volume of all voids within each hydrodynamic measurement zone, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(ii) if an emplacement hole is vertical, within the hydrodynamic measurement zones of either the emplacement hole or, at the option of the Testing Party, of the satellite hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, and television logging;

(iii) if an emplacement hole is horizontal, in the emplacement hole and associated satellite hole, as well as in the drilled holes specified in subparagraph (e)(ii) of this paragraph, caliper logs, directional surveys, geodetic measurements, and distance measurements to determine the dimensions and relative location of these holes, as well as measurements to determine the location and volume of all voids within each hydrodynamic measurement zone using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding; and

(iv) if an emplacement hole is horizontal, in the drilled holes specified in subparagraph (e)(ii) of this paragraph, and within the hydrodynamic measurement zones of the emplacement hole, or, at the option of the Testing Party, of the satellite hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, and acoustic logging;

(d) all logging data and geometrical measurements obtained by Designated Personnel, in accordance with subparagraph (c) of this paragraph, including calibration data, shall be duplicated, and a copy of the data shall be provided to personnel of the Testing Party prior to departure from the test site of Designated Personnel who have carried out these measurements. Calibration data shall include information necessary to confirm the sensitivity of logging equipment under the conditions in which it is used;

(e) Designated Personnel shall have the right to receive:

(i) if an emplacement hole is vertical, core samples or, at the option of Designated Personnel, rock fragments from the emplacement hole or, at the option of the Testing Party, from the satellite hole, extracted at no more than 10 depths within each hydrodynamic measurement zone, specified by Designated Personnel. The total volume of core samples or rock fragments extracted at each depth shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree; and

(ii) if an emplacement hole is horizontal, core samples or, at the option of Designated Personnel, rock fragments from the emplacement hole or, at the option of the Testing Party, the satellite hole within each hydrodynamic measurement zone. If core samples are extracted from the emplacement hole or, at the option of the Testing Party, from an excavated satellite hole, they shall be extracted during drilling from each of no more than 10 holes drilled at stations specified by Designated Personnel. The diameter of each drilled hole shall be no less than 0.09 meters and no more than 0.15 meters, and the depth of each hole shall be no more than the diameter of the emplacement hole or satellite hole at this station. Core samples shall be extracted at locations specified by Designated Personnel along each drilled hole. If core samples are extracted from a drilled satellite hole, they shall be extracted by personnel of the Testing Party during the drilling of the satellite hole, within each hydrodynamic measurement zone, at no more than 10 stations specified by Designated Personnel and under their observation. Rock fragments shall be extracted from the emplacement hole or an excavated satellite hole at each of no more than 10 stations specified by Designated Personnel. Core samples and rock fragments may be taken from no more than a total of 10 stations. If an emplacement hole or an excavated satellite hole is lined at any station specified by Designated Personnel for extracting core samples or rock fragments, personnel of the Testing Party shall enable Designated Personnel to extract core samples or rock fragments at such a station from native rock. The total volume of core samples or rock fragments extracted at each station shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree;

(f) core samples or rock fragments may be extracted in accordance with subparagraph (e) of this paragraph by personnel of the Testing Party, under observation of Designated Personnel, or by Designated Personnel, at the option of the Testing Party;

(g) if personnel of the Testing Party do not extract core samples or rock fragments in accordance with subparagraph (e) of this paragraph, Designated Personnel shall have the right, using their own equipment, to extract such core samples or rock fragments in accordance with subparagraph (e) of this paragraph, under observation of personnel of the Testing Party;

(h) if an emplacement hole is vertical, and if the Testing Party, prior to arrival of Designated Personnel at the test site:

(i) has cased a total of 20 meters or more of the emplacement hole or the satellite hole within any hydrodynamic measurement zone, Designated Personnel shall have the right to carry out, in the uncased hole, the activities specified in subparagraph (c)(ii) of this paragraph and to receive core samples or rock fragments from the uncased hole, extracted in accordance with subparagraphs (e), (f), and (g) of this paragraph; or

(ii) has cased a total of 20 meters or more of both the emplacement hole and the satellite hole within any hydrodynamic measurement zone, the Testing Party shall provide an uncased hole with respect to which Designated Personnel shall have the same rights as those specified for the emplacement hole and the satellite hole in subparagraphs (c), (e), (f), and (g) of this paragraph. The axis of this uncased hole shall be within 22 meters of the axes of the emplacement hole and the satellite hole within each hydrodynamic measurement zone. If personnel of the Testing Party, under observation of Designated Personnel, extract core samples through coring during the drilling of this uncased hole, the diameter of the hole shall be no less than 0.09 meters. If Designated Personnel, under observation of personnel of the Testing Party, extract core samples from this uncased hole following drilling, the diameter of the uncased hole shall be no less than 0.3 meters;

(i) Designated Personnel shall have the right to retain core samples and rock fragments specified in subparagraphs (e), (f), (g), and (h) of this paragraph. Any such core samples or rock fragments shall be prepared in accordance with procedures agreed upon by the Parties for shipment to the territory of the Verifying Party; and

(j) logging, directional surveys, geodetic measurements, and extracting of core samples or rock fragments carried out in accordance with subparagraphs (c), (e), (f), (g), (h), and (i) of this paragraph shall begin at times chosen by the Testing Party and specified in the coordinated schedule. Designated Personnel shall have the right, within a period not to exceed 21 days, to carry out logging, directional surveys, geodetic measurements, and coring activities, unless the Parties otherwise agree and so specify in the coordinated schedule. The Testing Party shall not emplace any explosive until the activities specified in this paragraph have been completed.

6. With respect to any explosion having a planned yield exceeding 50 kilotons and characteristics differing from those set forth in paragraph 2 or 3 of this Section with respect to a test of standard configuration:
(a) personnel of the Testing Party, using their own equipment and at a time of their own choosing, shall drill or excavate up to three satellite holes associated with the emplacement hole. The location of the satellite holes shall be determined in accordance with paragraph 11(b)(i) of Section XI of this Protocol. The Testing Party shall have the right to complete drilling or excavation of satellite holes for the specific test prior to the arrival of Designated Personnel at the test site for that test. The satellite holes shall meet the following requirements:
(i) with respect to the first satellite hole, its length shall be as specified in paragraph 4(a)(ii) of this Section;

(ii) with respect to the second and third satellite holes, if such are required by the Verifying Party, the axis of each satellite hole shall be within three meters of the axis specified by the Verifying Party. Its length shall be specified by the Verifying Party and in no case shall it extend beyond the hydrodynamic measurement zone associated with that explosion;

(iii) within each hydrodynamic measurement zone, the axis of each satellite hole shall be essentially parallel to the axis of the emplacement hole, if the emplacement hole is vertical, or shall be essentially straight, if the emplacement hole is horizontal. Within each hydrodynamic measurement zone, its axis shall be no less than eight meters from the axis of the emplacement hole, if the emplacement hole is vertical, or no less than 10 meters from the axis of the emplacement hole, if the emplacement hole is horizontal, and no less than six meters from the wall of any drilled or excavated cavity or hole;

(iv) with respect to a drilled satellite hole, it shall be drilled no less than 0.3 meters and no more than 0.5 meters in diameter, unless the Parties otherwise agree. Within each hydrodynamic measurement zone, no washouts shall penetrate more than one meter into the wall of the hole;

(v) with respect to an excavated satellite hole, it shall have a cross section, measured in the plane perpendicular to its axis, no greater than 2.5 meters by 2.5 meters within each hydrodynamic measurement zone; and

(vi) within each hydrodynamic measurement zone, except for any drilled or excavated cavity or hole, all voids, external and unconnected to any satellite hole, greater than 10 cubic meters in volume, within six meters of the axis of any satellite hole, and all voids greater than one cubic meter in volume, within two meters of the axis of any satellite hole, shall be filled with stemming material having a bulk density no less than 70 percent of the average density of the surrounding rock;

(b) Designated Personnel shall have the right to carry out, under observation of personnel of the Testing Party and with their assistance, if such assistance is requested by Designated Personnel, directional surveys and geodetic measurements of each satellite hole and emplacement hole prior to the beginning of emplacement of sensing elements and cables and transducers;

(c) equipment specified in paragraph 3 of Section VIII of this Protocol shall be operated by Designated Personnel and shall be installed, in accordance with installation instructions provided in accordance with paragraph 6(c) of Section VIII of this Protocol, by Designated Personnel under observation of personnel of the Testing Party and with their assistance, if such assistance is requested by Designated Personnel. The location of each hydrodynamic recording facility and the command and monitoring facility of the Verifying Party and the instrumentation facility of the Testing Party specified in paragraph 10(l) of this Section shall be determined by the Testing Party in consultation with the Verifying Party in the Coordinating Group no less than 90 days prior to the beginning of emplacement of sensing elements and cables. Areas for the installation of these facilities, cable supports, and cableways for protection of cables of the Verifying Party specified in paragraphs 3(b), 3(f), and 3(g) of Section VIII of this Protocol shall be prepared by the Testing Party in accordance with requirements agreed upon in the Coordinating Group. Only cables of the Verifying Party shall be installed in these cableways. Designated Personnel shall have access, under observation of personnel of the Testing Party, to the cables specified in paragraphs 3(f) and 3(g) of Section VIII of this Protocol and to the cableways in which they are installed, at all times. Personnel of the Testing Party shall have access to these cableways only under observation of Designated Personnel;

(d) Designated Personnel shall have the right to use their own primary electrical power sources to supply electrical power to hydrodynamic equipment specified in paragraph 3 of Section VIII of this Protocol. At the request of the Verifying Party, the Testing Party shall supply electrical power from the standard electrical network of its test site through converters provided by the Verifying Party or, upon agreement of the Parties, by the Testing Party;

(e) for each test, the only equipment installed in each satellite hole shall be that of the Verifying Party specified in paragraphs 3(a) and 3(h) of Section VIII of this Protocol. This equipment shall be installed in each satellite hole at the locations specified by Designated Personnel. Designated Personnel shall have the right to install in each satellite hole no more than six sensing elements and cables, without regard to the number of switches, and no more than six transducers together with no more than 14 cables for information transmission and power supply. The total number of cables in each satellite hole shall not exceed 20. Personnel of each Party shall have the right to measure the location of the installed sensing elements and cables and transducers;

(f) Designated Personnel shall have the right to conduct a final directional survey and geodetic measurements of each satellite hole upon completion of installation of sensing elements and cables and transducers;

(g) personnel of the Testing Party, under observation of Designated Personnel, shall fill all voids in or connected to each satellite hole within each hydrodynamic measurement zone with a stemming material agreed upon by the Parties, having a bulk density no less than 70 percent of the average density of the surrounding rock. A representative sample of no less than 1000 cubic centimeters in volume of each stemming material used in each hydrodynamic measurement zone shall be provided to Designated Personnel for retention. The methods and materials used for stemming satellite holes and any hydrodynamic measurement equipment emplacement pipe shall:

(i) be consistent with the containment practices of the Testing Party;

(ii) be chosen to minimize voids around sensing elements and cables and transducers; and

(iii) be chosen to avoid damage to the sensing elements and cables and transducers;

(h) Designated Personnel shall have the right to observe the stemming of the hydrodynamic measurement zones of each emplacement hole in accordance with paragraph 9(d) of this Section. A representative sample of no less than 1000 cubic centimeters in volume of each stemming material used in each hydrodynamic measurement zone shall be provided to Designated Personnel for retention;

(i) the Testing Party shall have the right to case or line each emplacement hole; and

(j) the Testing Party shall have the right to case or line each satellite hole, provided that:

(i) sensing elements and cables and transducers can be installed as specified in subparagraph (e) of this paragraph;

(ii) casing or lining material in each hydrodynamic measurement zone is agreed upon by the Parties; and

(iii) casing or lining in each hydrodynamic measurement zone is affixed to the surrounding formation with material agreed upon by the Parties.

7. In preparation for the use of the hydrodynamic yield measurement method with respect to any explosion having a planned yield exceeding 50 kilotons and characteristics differing from those set forth in paragraph 2 or 3 of this Section with respect to a test of standard configuration:
(a) upon their arrival at the test site, no less than 10 days prior to the planned date of the beginning of emplacement of sensing elements and cables and transducers, Designated Personnel shall provide the Testing Party with a description of the recording format and the computer program, to enable the Testing Party to read digital data if digital recordings of hydrodynamic data will be made by Designated Personnel;

(b) the Testing Party shall provide Designated Personnel upon their arrival at the test site with the results of any studies of core samples and rock fragments extracted from each emplacement hole and satellite hole and any exploratory holes and tunnels, and the results of logging and geodetic measurements carried out in each emplacement hole, each satellite hole, and any exploratory holes and tunnels, relevant to the geology and geophysics of each hydrodynamic measurement zone, if the Testing Party carried out such studies and measurements;

(c) using their own equipment and under observation of personnel of the Testing Party, Designated Personnel shall have the right to carry out:

(i) if an emplacement hole is vertical, in the emplacement hole and each associated satellite hole, caliper logs, directional surveys, geodetic measurements, and depth or distance measurements to determine the dimensions and the relative locations of the emplacement hole and each satellite hole, as well as measurements to determine the location and volume of all voids within each hydrodynamic measurement zone, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(ii) if an emplacement hole is vertical, within the hydrodynamic measurement zones of the emplacement hole and each associated satellite hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, and television logging;

(iii) if an emplacement hole is horizontal, in the emplacement hole and each associated satellite hole, as well as in the drilled holes specified in subparagraph (e)(ii) of this paragraph, caliper logs, directional surveys, geodetic measurements, and distance measurements to determine the dimensions and relative location of these holes, as well as measurements to determine the location and volume of all voids in each hydrodynamic measurement zone using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(iv) if an emplacement hole is horizontal, in the drilled holes specified in subparagraph (e)(ii) of this paragraph, and within the hydrodynamic measurement zones of the emplacement hole and each associated satellite hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, and acoustic logging; and

(v) magnetic surveys, in vertical satellite holes and drilled horizontal satellite holes, to obtain information necessary for the installation and positioning of transducers;

(d) all logging data and geometrical measurements obtained by Designated Personnel, in accordance with subparagraph (c) of this paragraph, including calibration data, shall be duplicated, and a copy of the data shall be provided to personnel of the Testing Party prior to departure from the test site of Designated Personnel who have carried out these measurements. Calibration data shall include information necessary to confirm the sensitivity of logging equipment under the conditions in which it is used;

(e) Designated Personnel shall have the right to receive:

(i) if an emplacement hole is vertical, core samples or, at the option of Designated Personnel, rock fragments from the emplacement hole and from each satellite hole, extracted at no more than 10 depths within each hydrodynamic measurement zone, specified by Designated Personnel. The total volume of core samples or rock fragments extracted at each depth shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree; and

(ii) if an emplacement hole is horizontal, core samples or, at the option of Designated Personnel, rock fragments from the emplacement hole and each satellite hole within each hydrodynamic measurement zone. If core samples are extracted from the emplacement hole or an excavated satellite hole, they shall be extracted during drilling from each of no more than 10 holes drilled at stations specified by Designated Personnel. The diameter of each drilled hole shall be no less than 0.09 meters and no more than 0.15 meters, and the depth of each hole shall be no more than the diameter of the emplacement hole or satellite hole at this station. Core samples shall be extracted at locations specified by Designated Personnel along each drilled hole. If core samples are extracted from a drilled satellite hole, they shall be extracted by personnel of the Testing Party during the drilling of the satellite hole, within each hydrodynamic measurement zone, at no more than 10 stations specified by Designated Personnel and under their observation. Rock fragments shall be extracted from the emplacement hole or an excavated satellite hole at each of no more than 10 stations specified by Designated Personnel. Core samples and rock fragments may be taken from no more than a total of 10 stations for each hole. If an emplacement hole or an excavated satellite hole is lined at any station specified by Designated Personnel for extracting core samples or rock fragments, personnel of the Testing Party shall enable Designated Personnel to extract core samples or rock fragments at such a station from native rock. The total volume of core samples or rock fragments extracted at each station shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree;

(f) core samples or rock fragments may be extracted in accordance with subparagraph (e) of this paragraph by personnel of the Testing Party, under observation of Designated Personnel, or by Designated Personnel, at the option of the Testing Party;

(g) if personnel of the Testing Party do not extract core samples or rock fragments in accordance with subparagraph (e) of this paragraph, Designated Personnel shall have the right, using their own equipment, to extract such core samples or rock fragments in accordance with subparagraph (e) of this paragraph, under observation of personnel of the Testing Party;

(h) if an emplacement hole is vertical, and if the Testing Party, prior to arrival of Designated Personnel at the test site, has cased a total of 20 meters or more of the emplacement hole or any satellite hole within any hydrodynamic measurement zone, and if within 22 meters from this cased hole there is no uncased hole with a diameter no less than 0.3 meters, the Testing Party shall provide an uncased hole for each hole so cased, with respect to which the Verifying Party shall have the same rights as those specified in subparagraphs (c), (e), (f), and (g) of this paragraph. Within each hydrodynamic measurement zone the axis of each uncased hole shall be no less than 11 and no more than 22 meters from such a cased hole. If personnel of the Testing Party, under observation of Designated Personnel, extract core samples through coring during the drilling of this uncased hole, the diameter of the hole shall be no less than 0.09 meters. If Designated Personnel, under observation of personnel of the Testing Party, extract core samples from this uncased hole following drilling, the diameter of the uncased hole shall be no less than 0.3 meters;

(i) Designated Personnel shall have the right to retain core samples and rock fragments specified in subparagraphs (e), (f), (g), and (h) of this paragraph. Any such core samples or rock fragments shall be prepared in accordance with procedures agreed upon by the Parties for shipment to the territory of the Verifying Party; and

(j) logging, directional surveys, magnetic surveys, geodetic measurements, and extracting of core samples or rock fragments carried out in accordance with subparagraphs (c), (e), (f), (g), (h), and (i) of this paragraph shall begin at times chosen by the Testing Party and specified in the coordinated schedule. Designated Personnel shall have the right, within a period not to exceed 25 days, to carry out logging, directional surveys, magnetic surveys, geodetic measurements, and coring activities, unless the Parties otherwise agree and so specify in the coordinated schedule. The Testing Party shall not emplace any explosive until the activities specified in this paragraph have been completed.

8. If the Verifying Party has notified the Testing Party that it intends to use the hydrodynamic yield measurement method with respect to a test of non-standard configuration having a planned yield exceeding 50 kilotons, and that it requires a reference test in accordance with paragraph 7 of Section III of this Protocol, the Testing Party shall provide for such a reference test for the non-standard test. To serve as a reference test, a test shall:
(a) have a planned yield exceeding 50 kilotons;

(b) be of standard configuration;

(c) have a single explosive canister;

(d) meet the following spacing criteria:

(i) the horizontal separation between the emplacement point of the reference test and each emplacement point of the non-standard test at which any explosive canister or its emplacement conditions differ from those specified for a test of standard configuration shall be no less than 300 meters and no more than 2000 meters;

(ii) each explosive canister of the test of non-standard configuration and the explosive canister of the associated reference test shall all be emplaced above the water table or shall all be emplaced below the water table; and

(iii) the depth of all emplacement points of the test of non-standard configuration shall be within 150 meters of the depth of the emplacement point of its associated reference test; and

(e) be conducted either prior to, or within 12 months following, the conduct of the test of non-standard configuration for which it serves as a reference test.
9. Designated Personnel shall have the right:
(a) to have access along agreed routes to the location of the test to carry out activities related to use of the hydrodynamic yield measurement method;

(b) to have access to their equipment associated with the hydrodynamic yield measurement method from the time of its delivery to Designated Personnel at the test site, until it is transferred to personnel of the Testing Party in accordance with paragraph 7(i) of Section VIII of this Protocol, unless otherwise provided in this Protocol;

(c) with respect to a test of standard configuration, as well as with respect to any explosion having a planned yield of 50 kilotons or less:

(i) if an emplacement hole is vertical, prior to the lowering of the explosive canister into the emplacement hole, to confirm by direct measurement the external dimensions of each explosive canister; to inspect visually the entire external structure of that canister and the choke section; to confirm by direct measurement that the choke section conforms to the specifications set forth in paragraph 2(c) of this Section; to observe continuously the explosive canister and any choke section from the time inspections and measurements, carried out in accordance with this subparagraph, begin; to observe the emplacement of the explosive canister into the emplacement hole and stemming of the emplacement hole from the time the entire explosive canister is last visible above the entrance of the emplacement hole until completion of stemming of each hydrodynamic measurement zone of the emplacement hole; to determine by direct measurement the depth of emplacement of the bottom part of any choke section; and to observe the stemming of the entire satellite hole; and

(ii) if an emplacement hole is horizontal, following placement of explosive canisters in the emplacement hole, and prior to the beginning of stemming around explosive canisters, to confirm by direct measurement the external dimensions of each explosive canister; to inspect visually the entire external structure of each explosive canister; to confirm by direct measurement that each choke section conforms to the specifications set forth in paragraph 3(e) of this Section; to observe continuously each explosive canister and each choke section from the time inspections and measurements, carried out in accordance with this subparagraph, begin, until the completion of stemming around each explosive canister and choke section, or, at the option of the Testing Party, until the explosive canister and choke section are fixed in place with solidified stemming material, in which case, after a period of no more than 24 hours for placement of explosives, to observe the explosive canister, the choke section, and the completion of stemming around each explosive canister and choke section; and to observe the stemming of each hydrodynamic measurement zone of the emplacement hole, the stemming of any access or bypass drifts, the stemming of any voids in each hydrodynamic measurement zone connected to the emplacement hole; and to observe the entire stemming of each associated satellite hole;

(d) with respect to any explosion having a planned yield exceeding 50 kilotons and characteristics differing from those set forth in paragraph 2 or 3 of this Section with respect to a test of standard configuration:
(i) if an emplacement hole is vertical, prior to the lowering of an explosive canister into the emplacement hole, to confirm by direct measurement the external dimensions of each explosive canister; to inspect visually the external structure of each canister and each choke section; to confirm by direct measurement that each choke section conforms to any specifications provided by the Testing Party in accordance with paragraph 10(c)(iii) of Section XI of this Protocol; to observe continuously each explosive canister and each choke section from the time inspections and measurements, carried out in accordance with this subparagraph, begin; to observe the emplacement of each explosive canister into the emplacement hole and stemming of the emplacement hole from the time an entire explosive canister is last visible above the entrance of the emplacement hole until completion of stemming of each hydrodynamic measurement zone of the emplacement hole; to determine by direct measurement the depth of emplacement of the upper surface of each explosive canister; and to observe the entire stemming of each associated satellite hole;

(ii) if an emplacement hole is horizontal, following placement of all explosive canisters in the emplacement hole and prior to the beginning of stemming around the explosive canister, to confirm by direct measurement the external dimensions of each explosive canister; to inspect visually the entire external structure of each explosive canister; to confirm by direct measurement that each choke section conforms to any specifications provided by the Testing Party in accordance with paragraph 10(c)(iii) of Section XI of this Protocol; to observe continuously each explosive canister and each choke section from the time inspections and measurements, carried out in accordance with this subparagraph, begin, until the completion of stemming around each explosive canister and choke section, or, at the option of the Testing Party, until the explosive canister and choke section are fixed in place with solidified stemming material, in which case, after a period of no more than 24 hours for placement of explosives, to observe the explosive canister, the choke section, and the completion of stemming around each explosive canister and choke section; to observe the stemming of each hydrodynamic measurement zone of the emplacement hole, the stemming of any access or bypass drifts, the stemming of any voids in each hydrodynamic measurement zone connected to the emplacement hole, except those voids and any access or bypass drifts designated by the Testing Party to remain unstemmed in accordance with paragraph 10(c) of Section XI of this Protocol; and to observe the entire stemming of each associated satellite hole; and

(iii) if a test is conducted in a cavity, to measure the shape and volume of the cavity after excavation and once again immediately prior to placement of explosive canisters with explosives or placement of explosives into explosive canisters. After placement of explosive canisters with explosives or placement of explosives into explosive canisters, Designated Personnel shall have the right to observe explosive canisters and to observe the stemming of each hydrodynamic measurement zone of the emplacement hole and any access or bypass drifts, and of any voids connected to the emplacement hole, within each hydrodynamic measurement zone, except those voids and any access or bypass drifts designated by the Testing Party to remain unstemmed, in accordance with paragraph 10(c) of Section XI of this Protocol; and to observe the entire stemming of each associated satellite hole;

(e) with respect to a test of standard configuration, as well as with respect to any explosion having a planned yield of 50 kilotons or less:
(i) if an emplacement hole is vertical, to unobstructed visual observation of the entrance to the emplacement hole and associated satellite hole from completion of stemming of the satellite hole and of the hydrodynamic measurement zones of the emplacement hole until departure of all personnel from the test location prior to the test; and

(ii) if an emplacement hole is horizontal, to unobstructed visual observation of sensing elements and cables until completion of stemming of each associated satellite hole, and of cables specified in paragraph 3(b) of Section VIII of this Protocol until completion of their installation in protective cableways specified in paragraph 4(d) of this Section, as well as observation of the entrance to the emplacement hole from completion of stemming of each satellite hole and of the hydrodynamic measurement zones of the emplacement hole until departure of all personnel from the test location prior to the test;

(f) with respect to any explosion having a planned yield exceeding 50 kilotons and characteristics differing from those set forth in paragraph 2 or 3 of this Section with respect to a test of standard configuration:
(i) if an emplacement hole is vertical, to unobstructed visual observation of the entrance to the emplacement hole and each satellite hole from completion of stemming of all satellite holes and the hydrodynamic measurement zones of the emplacement hole until departure of all personnel from the test location prior to the test; and

(ii) if an emplacement hole is horizontal, to unobstructed visual observation of the sensing elements and cables and transducers until completion of stemming of all associated satellite holes, and of cables specified in paragraph 3(b) of Section VIII of this Protocol until completion of their installation in protective cableways specified in paragraph 6(c) of this Section of the Protocol, as well as the entrance to the emplacement hole from completion of stemming of all satellite holes and the hydrodynamic measurement zones of the emplacement hole until departure of all personnel from the test location prior to the test;

(g) to monitor electrically the integrity and performance of their equipment specified in paragraphs 3(a), 3(b), 3(c), 3(d), 3(e), 3(f), and 3(g) of Section VIII of this Protocol and to observe continuously the cables specified in paragraphs 3(f) and 3(g) of Section VIII of this Protocol and the cableways in which they are installed as specified in paragraphs 4(d) and 6(c) of this Section, from the time emplacement of sensing elements and cables and transducers begins until departure of all personnel from the test location. Following departure of personnel and until reentry of personnel to the test location following the test, Designated Personnel shall have the right to observe remotely, by means of closed-circuit television, the surface area containing their hydrodynamic yield measurement equipment;

(h) to monitor electrically the integrity and performance of their equipment specified in paragraphs 3(a), 3(b), 3(c), 3(d), 3(f), and 3(g) of Section VIII of this Protocol from the command and monitoring facility specified in paragraph 3(e) of Section VIII of this Protocol, from commencement of its use by Designated Personnel until completion of the activities specified in paragraphs 9(m) and 14(b) of this Section;

(i) to transmit from the command and monitoring facility to each hydrodynamic recording facility the commands required for operation of that hydrodynamic recording facility;

(j) to use channels provided by the Testing Party within its telemetry system for transmission of information specified in subparagraphs (h), (i), (k), and (l) of this paragraph, if such a system is used at the test site of the Testing Party, or to use for these purposes its own cables, specified in paragraph 3(g) of Section VIII of this Protocol;

(k) to carry out hydrodynamic yield measurements and to record the hydrodynamic data;

(l) to transmit the hydrodynamic yield measurement data from each hydrodynamic recording facility to the command and monitoring facility; and

(m) to reenter the area containing each hydrodynamic recording facility at the same time as personnel of the Testing Party, and to have access, in accordance with procedures agreed upon by the Parties and accompanied by personnel of the Testing Party, to each hydrodynamic recording facility, for the purposes of retrieving and verifying the authenticity of recorded data and assessing the performance of the equipment of the Verifying Party during data recording and transmission.

10. During the carrying out of hydrodynamic yield measurements:
(a) the Representative of the Testing Party shall notify, in writing, the Designated Personnel Team Leader at the test site of the beginning of the period of readiness and the planned time of the test, in accordance with paragraph 13 of Section IV of this Protocol;

(b) the Testing Party shall produce an event readiness signal in the interval from seven to 15 minutes prior to the planned time of the test, as specified by the Verifying Party, with an accuracy of plus or minus 100 milliseconds. The parameters for this signal, produced by the Testing Party, and procedures for its transmission and reception shall be agreed upon by the Parties;

(c) Designated Personnel shall have the right to generate, using the trigger conditioner devices approved by the Parties, a timing reference signal using an electromagnetic pulse from their sensing elements and cables. This timing reference signal shall be generated, transmitted, and used by Designated Personnel without intervention by personnel of the Testing Party. For each explosion in a test, the trigger conditioner shall receive signals from one or two hydrodynamic yield measurement cables;

(d) Designated Personnel, under observation of personnel of the Testing Party, shall have the right to install the trigger conditioner devices. From the time of installation of these devices until the time of the test:

(i) Designated Personnel shall have the right to test and monitor the operation of the devices;

(ii) personnel of the Testing Party shall have the right to monitor the operation of the devices and to monitor and record the timing reference signal; and

(iii) neither Designated Personnel nor personnel of the Testing Party shall have physical access to the devices, except under observation of personnel of the other Party;

(e) the Testing Party shall provide, at the request of the Verifying Party, an electrical pulse corresponding to the nuclear explosion zero-time, with an accuracy of plus or minus one microsecond, for each explosion. The parameters for this signal and procedures for its transmission and reception shall be agreed upon by the Parties;

(f) the Testing Party shall have exclusive control over the generation of signals specified in subparagraphs (b) and (e) of this paragraph;

(g) Designated Personnel, under observation of personnel of the Testing Party, shall install in each cable from each satellite hole to a hydrodynamic recording facility an anti-intrusiveness device for interrupting the transmission, from the sensing elements and cables and transducers to the hydrodynamic recording facility of the Verifying Party, of any signal unrelated to hydrodynamic yield measurements. These devices shall be provided by the Testing Party from among those approved by both Parties and shall not interfere with the ability of Designated Personnel to record data required for hydrodynamic yield measurements of each explosion in a test. From the time of installation of these devices until the final dry run, personnel of each Party shall have the right to test and monitor the operation of the devices and to have physical access to them only under observation of personnel of the other Party. Sole control over the triggering of these devices shall be transferred to the Testing Party at the time of departure of all personnel from the test location prior to the test;

(h) each hydrodynamic recording facility shall have an independent grounding loop with an impedance no greater than 10 ohms;

(i) the shields of all cables associated with sensing elements and cables and transducers of the Verifying Party shall be grounded:

(i) at the input to each hydrodynamic recording facility of the Verifying Party;

(ii) at the output of each anti-intrusiveness device;

(iii) at the input of each trigger conditioner device; and

(iv) in those cables associated with sensing elements and cables in which no trigger conditioner device is installed, at the input of the anti-intrusiveness device;

(j) grounding of each hydrodynamic recording facility, as well as grounding of cables associated with the sensing elements and cables and transducers of the Verifying Party, shall be carried out by Designated Personnel under observation of personnel of the Testing Party. The grounding system of each hydrodynamic recording facility, as well as of cables associated with the sensing elements and cables and transducers shall be under the joint control of the Parties;

(k) Designated Personnel shall have the right to install, under observation of personnel of the Testing Party, an isolation transformer at the input of each anti-intrusiveness device or trigger conditioner device. From the time of installation of these devices until the time of the test, neither Designated Personnel nor personnel of the Testing Party shall have physical access to these devices, except under observation of personnel of the other Party;

(l) the Testing Party shall have the right to install, at a distance of no less than 50 meters from each hydrodynamic recording facility, a facility containing instrumentation for monitoring and recording the timing reference signal, for controlling and monitoring the operation of the anti-intrusiveness devices, and for the transmission of control and trigger signals. Signals between the instrumentation facility of the Testing Party and each hydrodynamic recording facility shall be transmitted over fiber optic cables. The Testing Party shall provide for the installation, in each hydrodynamic recording facility, of terminal devices for converting optical signals into electrical signals produced in accordance with subparagraphs (b) and (e) of this paragraph, and for monitoring the interval of interruption and for monitoring the power supply of the anti-intrusiveness device, in accordance with subparagraph (g) of this paragraph. The Verifying Party shall provide for the installation in the facility of the Testing Party of a terminal device for converting an optical signal into an electrical time referencing signal provided in accordance with subparagraph (d)(ii) of this paragraph. These provided devices shall be installed under observation of personnel of both Parties and sealed by the Party providing the device. The instrumentation facilities specified in th